Project Updates

Construction Update Aerials - May 2017

Click on each aerial to enlarge image.

Construction Update Aerials - April 2017

Click on each aerial to enlarge image.

Construction Update Aerials - November 2016

Click on each aerial to enlarge image.

Temporary Closure of Chamblee Rail Trail Starting October 10

Oct. 3, 2016 – CONNOLLY, developers of Parkview on Peachtree, will implement a temporary closure the Chamblee Rail Trail beginning Monday, Oct. 10, for construction of retaining walls.  The closure will affect the area of the Rail Trail between the Peachtree Boulevard underpass and Keswick Park.

 

Construction fencing will be installed for public safety and signs will be posted at each end of the trail to notify pedestrians of the closure. For more information and updates on this project, contact CONNOLLY at (770) 277-8000 or visit http://parkviewonpeachtree.com.

Chamblee Rail Trail Reopened Today

We are pleased to announce the section of the Chamblee Rail-Trail near our site will reopen this evening. Happy walking everybody and stay tuned for future site updates. #ParkviewMyLife

Construction Update Aerials - September 2016

Click on each aerial to enlarge image.

Construction Update Aerials - August 2016

Click on each aerial to enlarge image.

Construction Update Aerials - July 2016

Click on each aerial to enlarge image.

Construction Update Aerials - June 2016

Click on each aerial to enlarge image.

Groundbreaking Celebration Lunch - May 19

Click on each to enlarge image.

Construction Update Aerials - May 2016

Click on each aerial to enlarge image.

New Plaza Rendering

Click on rendering to enlarge image.

Portion of Chamblee Rail Trail to Remain Temporarily Closed

March 29, 2016 – CONNOLLY, developers of Parkview on Peachtree, announced today the Chamblee Rail Trail section from the ball park to the tunnel under Peachtree Boulevard will remain closed due to construction. Unfortunately, the delays are due to weather and unforeseen utility relocation issues.

 

With public safety in mind, pedestrian fencing and signs will remain posted at each end of the trail to notify pedestrians of the closure until further notice. Once complete, the new section of the trail will be available for pedestrians.

 

For more information and updates on this project, contact CONNOLLY at (770) 277-8000 or visit http://parkviewonpeachtree.com.

New Renderings - March 2016

Click on each rendering to enlarge image.

Construction Update Aerials - March 2016

Click on each aerial to enlarge image.

Construction Update Aerials - February 2016

Click on each aerial to enlarge image.

Temporary Closure of Chamblee Rail Trail

December 18, 2015 – CONNOLLY, developers of Parkview on Peachtree, will implement a temporary closure of a portion of the Chamblee Rail Trail for construction work beginning on or around December 27.  The closure — which is necessary to allow completion of needed utility and trail relocation — will affect the trail from the Keswick Park softball field to the tunnel under Peachtree Boulevard for approximately 90 days depending on weather, at which time the new relocated section of the trail will be put in place.

 

Fencing will be installed for the safety of pedestrians and signs will be posted at each end of the trail to notify pedestrians of the closure.

 

For more information and updates on this project, contact CONNOLLY at (770) 277-8000 or visit http://parkviewonpeachtree.com.